What Are Site Costs and how are they worked out?
Site costs are everything required to turn your particular piece of ground into something a house can stand on. They are calculated, not estimated, and the calculation begins with two reports that most buyers never see: a soil test and a feature survey.
What actually happens in a soil test?
A geotechnical contractor attends the block and takes bore holes at several points, generally to a depth of a few metres. Samples are recovered from each, logged by depth, and taken away for analysis.
What the laboratory is measuring is how much the ground moves when its moisture content changes. Clay swells when wet and shrinks when it dries. That movement, repeated over seasons, is what cracks slabs and distorts frames if it is not designed for.
The result is a classification, and the classification is a prediction of how much the surface will rise and fall. Stable sand or rock barely moves. Moderately reactive clay moves a noticeable amount. Highly and extremely reactive clay move a great deal, and sites with fill or soft soil get their own category requiring individual engineering.
It is worth knowing that classification is a prediction rather than a measurement of today. The engineer is designing for the worst combination of wet and dry the site is likely to see over decades, which is why a block that looks perfectly firm in summer can still return a reactive result. Buyers occasionally query this on the basis of how the ground appears on the day, and the answer is that the report describes seasonal behaviour rather than a single moment. The feature survey runs alongside it, recording levels across the block, the position of services, existing structures, trees and boundaries. Between the two reports, the engineer has what they need.
How does a classification become a cost?
Six things the engineer decides once the reports arrive, each of which carries a price.
Slab type and depth
Reactive ground needs a stiffer raft with deeper edge beams and more steel. The more the ground moves, the more slab is required to resist it.
Beam spacing and reinforcement
Internal beams and the reinforcement within them are specified to the predicted movement rather than to a standard detail.
Cut and fill volume
Taken from the survey levels. The volume of soil moved, compacted or carted determines this line precisely rather than approximately.
Retaining requirements
Any point where the ground steps up or down against a neighbour needs a wall designed to hold it. That is engineering rather than gardening, and it is costed accordingly.
Footing depth through fill
Where uncontrolled fill is found, footings may need to reach through it to competent material, which adds both engineering and excavation.
Service connection runs
Measured from the survey. The distance from each connection point to where it enters the house is a real and variable cost.
What should a site costs schedule contain?
A genuine schedule is itemised. If yours is a single line, ask for it to be broken down.
| Line item | What it covers | How it is determined |
|---|---|---|
| Soil test and survey | The investigation itself | Fixed cost, commissioned early |
| Slab and footings variation | The engineered slab above a base design | Soil classification and engineer's design |
| Cut and fill | Levelling the building platform | Volume calculated from survey levels |
| Rock removal | Breaking out and carting rock | Only if encountered, quantified from bore logs |
| Retaining | Structural walls holding level changes | Engineered where boundaries require it |
| Service connections | Water, sewer, power, gas, telecommunications | Measured runs from the connection points |
| Estate or council requirements | Facade rules, crossovers, tree protection | Read from the guidelines and the permit |
Swipe the table sideways to see every column.
Our cost guide places this schedule within the five blocks of a total build budget.
What is wrong with a site costs allowance?
Nothing, provided everybody understands it is a placeholder rather than a price. The difficulty is that allowances are frequently presented in a way that reads like a price.
An allowance is a number a builder inserts before the block has been investigated, usually set at a level that keeps the headline figure competitive. When the reports eventually arrive, the real cost is compared against the allowance and the difference is passed to you.
That means the direction of the surprise is not random. If allowances were routinely set generously, builders would lose work at quoting stage to those who set them lean. The commercial pressure runs one way.
The alternative is straightforward and costs a few hundred dollars: test the block first, then price it. We do it that way because it removes the largest variable in the project before anybody signs, and because a fixed price with an untested site underneath it is not really fixed.
What should you ask about site costs?
Six questions that reveal whether a quote is priced or estimated.
Questions about site costs
Send us a block and we will arrange the testing and show you exactly how the resulting figure was reached.
Ask us about your buildWhat exactly are site costs?
How much does a soil test cost and who pays?
What does a soil classification actually mean?
Can site costs still change after I sign?
Why are site costs higher on some blocks?
Want your block tested before you commit?
Send us the address or the lot details. We will arrange the soil test and survey and show you an itemised site costs schedule rather than a single line.