How Construction Loans and progress payments work
A construction loan does not deposit the full amount into your account. It sits approved and mostly undrawn, releasing money to the builder only as each stage of work is finished and verified. You pay interest solely on what has been advanced, which is why repayments begin small and climb as the house does.
How does the money actually move?
Your builder completes a stage, then issues a progress claim for the amount attached to it in the contract. That claim goes to you and to your lender.
The lender does not simply pay it. In most cases a valuer or inspector attends the site to confirm the work claimed has genuinely been completed to the standard expected. Only after that verification does the money move, and it moves to the builder rather than to you.
That sequence protects you more than it might appear. It means nobody is paid for work that does not exist, and it gives an independent party a look at the site at five separate points during construction.
It also means delays in inspection become delays in payment, and delays in payment can become delays in work. Where a lender's valuer is slow to attend, the effect ripples through the programme, which is why we keep clients informed about claims rather than leaving them to discover a hold up later.
What is claimed at each stage?
Five claims across a typical build, each verified before release.
| Stage | What must be complete | What the inspector confirms |
|---|---|---|
| Base | Site prepared, footings and slab poured | The slab exists, is to the engineered design and matches the plans |
| Frame | Wall frames and roof trusses erected | The structure is up, braced and set out correctly on the slab |
| Lock-up | Roof, external cladding, windows and doors in | The building is weathertight and can be secured |
| Fixing | Internal linings, doors, cabinetry, skirting | Internal fit-out is substantially complete |
| Completion | All work finished, cleaned and ready | The home is complete and matches the contract documents |
Swipe the table sideways to see every column.
Percentages attached to each stage are set by the contract and are regulated in Victoria, so a builder cannot front-load claims arbitrarily.
How is interest charged during a build?
Six things about the interest position that catch first-time builders out.
Only on drawn funds
Interest accrues on money actually advanced, not on the approved limit. At base stage you are paying on a fraction of the total.
It climbs each stage
Each release adds to the balance, so repayments increase progressively through the build rather than jumping at the end.
Usually interest only
Most construction loans run interest only during the build, so you are not reducing principal while the house is being built.
Land interest starts first
If the land settled before construction began, you have been paying interest on that portion since settlement.
Rent runs alongside
Unless you are living elsewhere rent free, you are covering accommodation and interest simultaneously for the whole build.
It converts at handover
Once the final claim is paid the loan typically reverts to a standard principal and interest mortgage.
What happens if something goes wrong?
Three situations come up often enough to plan for.
The first is a delayed inspection. Where the lender's valuer takes longer than expected, payment is held and the builder may pause work on a site where they are not being paid. It is usually resolved by a phone call, but it needs somebody chasing it, and that somebody is more often the client than either the bank or the builder. Knowing that in advance is worth a great deal, because a week lost at lock-up stage in winter can cost considerably more than a week lost elsewhere in the programme.
The second is a valuation shortfall. If the lender's valuation of the completed property comes in below expectations, they may reduce what they will advance, leaving you to cover a gap you had not planned for. This is more likely where the market has moved or where the specification is unusual for the area.
The third is a variation you requested. Changes you approve mid build are generally not covered by the original approval, so they are typically paid from your own funds rather than added to the loan. That surprises people, and it is one more argument for settling structural decisions at tender rather than at frame stage.
How do you keep the finance side smooth?
Six habits that prevent most funding problems on a build.
Questions about construction lending
We are builders rather than brokers, but we work alongside lenders on every project and can tell you how the process usually runs.
Ask us about your buildDo I get the whole loan at once?
How much interest will I pay during the build?
Who inspects the work before payment?
Can I add a variation to my construction loan?
What happens to the loan when the house is finished?